Why anchorage changes the plan
When a vessel is alongside, a crew change is mostly a ground transport exercise: meet the joiners at the airport, drive them to the quay, walk them up the gangway. At anchorage, the last leg becomes a marine operation. People and baggage must travel by launch boat across open water, and the vessel has to be ready to receive them in conditions that are safe for everyone on the ladder.
That difference changes who needs to be involved. Alongside, the agent, the transport provider and the ship's officers are enough. At anchorage, a suitable boat, a competent crew for it, port permission to move and a master who is ready to take the transfer all have to line up at the same time.
For ship managers rotating crew in Nigeria, the first planning question is therefore simple: will the vessel be at anchorage or alongside on the rotation date? If nobody can answer yet, plan for anchorage until she is confirmed alongside.
Choosing and briefing the launch
Not every boat that can reach an anchored ship is suitable for carrying seafarers with kitbags. Think about passenger capacity, deck space for baggage, seating and handholds, lifejackets for every person and a boat that can come alongside the pilot ladder or accommodation ladder without damage to either side.
Ask for the boat's details early and share them with the master and the manager's marine department, so that the ship's own transfer arrangements can be matched to the boat that will actually arrive. Agree who will be on the ladder, who counts heads, and how baggage will be passed so that nobody carries a heavy bag while climbing.
Joiners and leavers should travel in one planned movement where possible. Two separate trips double the exposure to weather and the demand on the vessel's deck crew, and they make it harder to confirm that everyone who was meant to leave has left.
Timing, daylight and weather margins
A transfer at anchorage is most comfortable in daylight and in a calm sea. Sea state and swell can change through the day, so the plan should name a preferred window and a second window, rather than one fixed hour that has to be met whatever the conditions.
Work backwards from the vessel's own timetable. If she is due to sail after cargo operations, the transfer must finish with enough margin that a delayed boat does not become a delayed departure. If she is waiting for a berth, remember that the berth call can come at short notice and may overtake a transfer planned for later in the day.
Agree a decision point with the master and the manager: a time by which the transfer either goes ahead or moves to the fallback. Having that point written down avoids a debate on the radio while people are already waiting on the jetty.
Documents and ground movements before the launch
The launch is the last part of a longer chain. Seafarer documents need to match the crew list, visas or invitations need to be in place for those who need them, flights should arrive with room to spare, and meet-and-assist should be waiting at the airport.
Hotels and ground transport matter more at anchorage than alongside, because a transfer that slips overnight leaves joiners who still need a bed and leavers who still need a flight. Hold a hotel option and a flexible ticket for anyone whose onward travel depends on the transfer happening on the planned day.
Keep one movement plan that lists each person, their document status, their transport to the jetty, their launch seat and their next step after the transfer. Anyone looking at the plan should be able to see where every individual is.
Planning your next anchorage crew change with Vandyvah
Vandyvah's operations team coordinates crew changes in Nigerian ports, including transfers by launch boat where a vessel is at anchorage. We work with the manager and the master on the movement plan, the transfer window, the ground transport and the fallback, and we keep everyone updated as the vessel's position and the sea conditions change.
If you have a rotation coming up for a vessel that may be at anchorage, contact the operations team before the vessel arrives. A short conversation about the crew list, the ETA and the preferred transfer window is the best way to make the day itself uneventful.
Anchorage crew change checklist
- transfer method confirmed as anchorage or alongside
- launch boat details shared with the master and manager
- preferred and second transfer windows agreed
- decision point set for going ahead or using the fallback
- crew list matched to passports and seafarer documents
- flights, hotels and meet-and-assist confirmed for every person
- baggage handling and ladder arrangements briefed to the vessel
- fallback date and onward travel options held
Where delay usually develops
- no launch boat confirmed until the vessel has already arrived
- sea state or swell making the planned window unsuitable
- the vessel's berth call or sailing time moving after transport is committed
- crew list details that do not match travel documents
- flights landing too late for the daylight transfer window
- no fallback date or hotel for people who cannot transfer on the day
What the principal should prepare
- the vessel's position, ETA and expected anchorage or berth
- a complete crew list with document details
- flight itineraries or ticketing authority
- the master's requirements for ladder and baggage handling
- authority for local spend and contingency decisions
What Vandyvah can coordinate
- a movement plan covering every joiner and leaver
- launch boat arrangements for the anchorage transfer
- airport meet-and-assist and ground transport to the jetty
- hotel arrangements for people who wait or arrive early
- live updates as the vessel, the weather or the flights change
- confirmation once each person is on board or on their way home